EPC Projects: Transportation of Big Equipment in Difficult-Access Areas

epc projects

EPC projects are highly schedule driven. In order to complete these massive projects early as possible, the different phases of the project are overlapped. However, EPC projects still face challenges with a cost overrun and schedule delays. A case study on problems and practices in EPC project management has revealed that one of the sources of these challenges is related to material and equipment. Transportation is one of the big issues here.

EPC Projects (Engineering, Procurement, and Construction)

Let’s see a case study EPC project of Copper Concentrator Plant located in Central Chile shown in the figure below.Transport1

Source: https://web.stanford.edu/class/cee320/CEE320C/RobertFoxPresentation.pdf

The following parameters say how big the project is and how difficult the transportation is, to the 10500ft uphill filled with snow.

  • Two sites connected by a 57 km pipeline
  • 8,000,000 cubic meters of earth-works
  • 400,000 cubic meters of structural concrete
  • 18 tons of structural steel
  • 1,200+ Equipment tag items
  • 120,000 meters of piping (1,700 line nos.)
  • Plant capacity: 110,000 tons per day
  • Investment $2.5B

Transport2

Source

The figure shows that transportation and installation cost is the same as that of equipment and material cost. It reveals that transportation adds a significant cost component to the project.

In order to overcome the challenges faced by EPC projects on transporting big equipment to difficult access areas, there are efforts already successful and few such examples are discussed in this article.

Electricity is not only for urban areas. Electric pole installations with challenging terrain are made easy nowadays. Compared to traditional pole materials, smaller helicopters can be used to lift fully constructed H-frames of lightweight composite poles for challenging location drops as shown below.

Transport3 Transport4

 

 

 

 

 

 

 

Source: http://www.rspoles.com/rs-poles/

Wind turbine blades are another challenging object to transport. Not only the size of the blade, but also the constrained access roads are common in such applications. See how difficult to transport fully assembled wind rotor with a diameter of 118 meters and weight about 150 tons.

Transport5

Source: http://www.rlocman.ru/review/article.html?di=125796

One another constraint as shown below is the very steep roads creating traction issues in trying to get the equipment up to the site.Transport6

Source: http://www.transoftsolutions.com/newsletter/detail/1013casestudy1

An even more difficult situation is shown in the below figure on a mountain road in the Swiss Alps. Such complex problems need the most sophisticated solutions. The vehicle uses a special adapter for mounting the blades which can raise it to 23 °, lower, and rotate to the left or right using a hydraulic actuator making the blade floatable above the surrounding obstacles. Further, with the purpose of reducing wind load, this adapter has been designed with the ability to rotate about the longitudinal axis of the blade.

Transport7

Source: http://www.rlocman.ru/review/article.html?di=125795

A good alternative would be using Zeppelins. A California based company is working on an Aeroscraft; a variable buoyancy vehicle that has the ability to off-load without re-ballasting. Its vertical takeoff and landing capability enable transporting to destinations like uneven ground.

Transport8

Source: http://www.windpowerengineering.com/news/have-you-heard-of-the-aeroscraft/

One example of transporting heavy generators to the power plants is shown below. The situation is complex with three constraints; passing underneath low bridges across a river, cross a number of long bridges, and up and down extreme slope gradients on land.

A drive-in pontoon has been used to pass the load underneath the low bridges across the rivers. Further, in order to cross the long bridges on land, part of the load on the Hydraulic Platform trailer has been placed on large skid beams. Also, to cope with extreme slope gradients, SPT units consisting of 16 axle lines have been used. See pictures below

Transport10 Transport9

Another good example is transporting big penstocks for a hydropower plant site. If the plant is only accessed by water what else we should expect? See below figure

Transport11

The below figure is another example of transporting off-site modularised large wet flue gas desulfurization sections by river barge and on the active roadway before installing at this coal-fired power plant.

Transport12

 

Source: http://www.babcock.com/library/Documents/SP-590.PDF

Last, but not least let’s see how locals have constructed a helicopter landing site in the jungle with logs enabling their clients to access a tribe few have ever seen.

Transport13

Source: http://www.superyachttimes.com/editorial/77/article/id/11741

Do you like reading about transportation challenges? Do you enjoy solving engineering challenges?

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Logo ministerio de economia y competitividad gobierno de españa logo ICEX logo feder seal of excellence  logo chile startuplogo innovo

©2020 Ennomotive Engineering Competitions - Legal Info ENNOMOTIVE SL, as part of the ICEX Next - Introduction to Export Program, has received support from ICEX and funding by FEDER, the European Fund. The goal of this support is to contribute to the international development of the company.

 

Ennomotive will help you solve your technological challenges. If you have any questions about our open innovation platform, please contact us.

Log in with your credentials

Forgot your details?